Update documentation
This commit is contained in:
@@ -41,3 +41,20 @@ Categories are not global to the application but attached to a project.
|
||||
Each project can have different categories.
|
||||
|
||||
However, if you always create the same categories for all your projects, you can define here the list of categories to create automatically.
|
||||
|
||||
### Allow only one subtask in progress at the same time for a user
|
||||
|
||||
When this option is enabled, a user can work with only one subtask at the time.
|
||||
|
||||
If another subtask have the status "in progress", the user will see this dialog box:
|
||||
|
||||

|
||||
|
||||
### Enable time tracking for subtasks
|
||||
|
||||
When this option is enabled, each time the status of a subtask is changed, the start time and the end time are recorded in the database for the assignee.
|
||||
|
||||
- When the status changes to "in progress" then the start time is saved
|
||||
- When the status changes to "done" then the end time is saved
|
||||
|
||||
The time spent for the subtask and the task is also updated.
|
||||
|
||||