Update documentation

This commit is contained in:
Frederic Guillot
2015-02-21 21:05:56 -05:00
parent 2b3f0b6179
commit 19d061db71
7 changed files with 122 additions and 0 deletions

View File

@@ -41,3 +41,20 @@ Categories are not global to the application but attached to a project.
Each project can have different categories.
However, if you always create the same categories for all your projects, you can define here the list of categories to create automatically.
### Allow only one subtask in progress at the same time for a user
When this option is enabled, a user can work with only one subtask at the time.
If another subtask have the status "in progress", the user will see this dialog box:
![Subtask user restriction](http://kanboard.net/screenshots/documentation/subtask-user-restriction.png)
### Enable time tracking for subtasks
When this option is enabled, each time the status of a subtask is changed, the start time and the end time are recorded in the database for the assignee.
- When the status changes to "in progress" then the start time is saved
- When the status changes to "done" then the end time is saved
The time spent for the subtask and the task is also updated.